Project Management Dashboard

πŸ”’ Planning starts β€” πŸ”’ Festival β€”
Loading schedule…
Viewing as β€” Β· Switch Β· Planning and festival dates are fixed. Contact the PM to request a change.
Refresh daily. This tool is updated frequently β€” an open tab may be running an outdated version.
Critical path β€” next 30 / 60 / 90 days

Everything scheduled to start in each window, sorted by float β€” lowest first, so the tightest items surface even when there's real slack overall.

Status breakdown
Progress by workstream
Planned vs. actual completion
Behind schedule
Hard constraints due within 90 days

Fixed-date/time activities due within 90 days, or in conflict. Red indicates upstream logic is tracking later than the fixed date allows.

Date has moved

Edits that changed the calculated festival date. All other edits are recorded in the Change Log.

See full change log β†’
Active now

Refreshes every 10 seconds.

On logic (non-critical) Critical path Milestone Open end (no logic)
Select an activity to view calculated dates or edit its logic, duration, and owner.
Go / No-Go Gates

Minimum conditions required for the festival to proceed. Independent of overall schedule status.

IDGateTarget dateStatus
Critical path: activities with zero total float. Any delay to these directly delays the calculated finish date. This is a technical schedule-risk view, not a priority list β€” see Go/No-Go above for the handful of items that actually determine whether the festival happens. Split below by whether the item is needed by the festival's real end date (Aug 22) or only afterward, for closeout.
Critical, needed by Aug 22
IDActivityWorkstreamDurEarly StartEarly FinishTotal Float
Critical to closeout only (after Aug 22)

Zero float relative to completion of the full register, including post-festival administrative work β€” not the festival date itself. For closeout planning, not festival-risk review.

IDActivityWorkstreamDurEarly StartEarly FinishTotal Float
Feeding buffers β€” network configuration

Merge points where a non-critical activity feeds directly into the critical path. Buffers here absorb delay on the feeding side without adding float to the critical path itself. New merge points default to 2 working days; adjustable.

Resource basis: Owner Role per the activity register. Totals reflect scheduled working days for logic-linked activities only; unlinked (open-end) activities are excluded until connected.
Activities with no predecessor logic. Expected count: one (GOV-010, the project start milestone).
IDActivityWorkstreamTypeOwnerLogic Status
Full edit history. Rows in red indicate a change that altered the calculated festival date.
Contribution summary, by person
PersonTotal changes loggedTasks marked completeLast activity
Usage log
PersonLast seenChanges made
Role-to-person assignment. Aggregate workload by person is shown on the Resource Loading tab.
Owner Role (from register)ActivitiesAssigned to
LBFF β€” Board Meeting Schedule
Default cadence: monthly (more than 4 months out), biweekly (8 weeks to 4 months out), weekly (within 8 weeks). Standard time: Monday, 3:00 PM. Date and time editable per meeting. Agendas generated from current schedule status.
#
Phase
Date
Time
Risk assessment β€” Rev 0. All fields editable.
Weather β€” Aug 19–22, historical data

Historical climate data (NOAA, 55-year average) for these dates. Not a forecast. Forecast data becomes available approximately 10–16 days before the event.

IDCategoryRiskProb %ImpactOwnerMitigationStatus
Starting balances are estimates based on prior-year scale. All entries editable; add transactions as they occur.
Cash position β€” running ledger

Deposit and Payment entries affect bank balance directly. Reserved (active PO) and Approved (ready to pay) do not affect bank balance but reduce Available funds. Reclassify to Payment once funds are disbursed.

DateDescriptionCategoryTypeAmount
Cash needs by date

Projected cash outflows by date and amount. Dates are drawn from the schedule where available; amounts are estimates pending confirmation.

DateAmountWhat it's forSchedule source
No sign-in exists yet, so approval buttons are visible to everyone the same way every other edit in this tool is β€” this tracks the real workflow status, but doesn't technically restrict who can click Approve. That needs the password system still on the list.
Submit an expense
All expenses
DateSubmitted byCategoryDescriptionAmountReceiptStatus
Approve is restricted to the Board President. Mark Received is restricted to whoever requested the PO. Mark Paid is restricted to the Treasurer/Finance Lead. None of this is enforced by a real login yet β€” it's hidden by name match, not secured. Real sign-in is still on the list.
Submit a purchase order
All purchase orders
Requested byVendorCategoryDescriptionAmountNeeded byQuoteVendor invoiceStatus
Visible to everyone with the tool open. Not private messaging β€” treat it like a shared board channel.
The suggestion is signed with your name. Votes are not β€” the count is real, who voted for it isn't shown to anyone.
Add a suggestion
All suggestions
Permanent, dated snapshots. Once saved, a report card does not change β€” even if the underlying schedule is edited later. This is a historical record, not a live view.
Take a snapshot

Grading basis: on-time completion rate of tasks that have actually reached their due date. A person with zero tasks assigned is marked No Participation, not graded on a curve with everyone else. A person with tasks assigned but nothing due yet is marked Pending.

History
Everything where you're Accountable, per the RACI field on each activity. Switch identity in the header to see a different person's view.
Behind schedule
Due in the next 30 days
Everything else assigned to you
IDActivityWorkstreamStartStatus
Draft staffing plan β€” Rev 0. Headcounts, roles, and shift times are placeholders pending confirmation with the team.
Role / TaskVolunteersReports toStartEndNotes
πŸ“Š
Dashboard
The quick look. Are we on time? What's behind?
πŸ“‹
Schedule
Every task. Click one to check it off or change it.
πŸ”₯
Critical Path
These can't be late β€” or the festival date moves.
πŸ‘₯
Resource Loading
Shows who has too much on their plate.
❓
Open Ends
Tasks nobody's connected to a plan yet.
πŸ§‘β€πŸ€β€πŸ§‘
Team
Who owns what.
πŸ“…
Board Meetings
When we meet. Click "Agenda" to see what to talk about.
⚠️
Risk Register
What could go wrong, how likely, who owns it.
πŸ’°
Finance
What's in the bank, what's reserved, what's coming due.
🧾
Expenses
Submit an expense with a receipt, track it to paid.
πŸ“¦
Purchase Orders
Request a PO, track it from approved to paid.
πŸ’¬
Chat
Leave a note for the whole group.
πŸ’‘
What Can We Do Better
Suggest and vote β€” suggestions are signed, votes aren't.
πŸ“‹
Report Card
A permanent monthly snapshot β€” board and individual grades.
πŸŽͺ
Event Day Staffing
Who works during the festival, and when.
βœ…
My Tasks
Your own view β€” just what's on your plate.
πŸ“
Change Log
Every change, who made it, when.
How to check off a task
  1. Go to Schedule, find your task, click it.
  2. Change the status to Complete.
  3. Click Apply.
Three things to know
Colors
On track Can't be late Milestone
Dates that can't move

Planning starts Nov 1, 2026. The festival is Aug 19–22, 2027. Locked β€” ask if these ever need to change.